Two people drowned earlier this month at the Umdloti River crossing north of Durban. The site of a new bridge construction project that has been stalled since 2018. An explanation for which the KwaZulu-Natal Department of Transport, Community Safety and Liaison has failed to give.
Two people drowned in the Umdloti River during heavy rains. The old bridge between Ndwedwe and Verulam had collapsed during flooding.
In February last year, department spokesperson Kwanele Ncalane told GroundUp that the R66 million contract to build the bridge had been terminated because the contractor could not meet the specifications of the contract. He said then that the department was busy finalising specifications and would re-advertise the contract.
“The process normally takes approximately six months for the contract to be awarded and another 42 days to get the Construction Work Permit so that the contractor can start construction,” he said.
Ncalane said once construction started, work on the bridge was expected to take 12 months.
But nearly a year later, no progress has been made on the bridge. Residents have been forced to use the old bridge.
After the collapse of the old bridge and the loss of two lives, KwaZulu-Natal Premier Sihle Zikalala, and the MEC for Transport, Community Safety and Liaison, Peggy Nkonyeni, visited Ndwedwe. Zikalala promised that a new contractor would be on site within the next three months.
But neither Zikalala nor Nkonyeni explained why nothing had been done since last February.
Our attempts to get answers to this and other questions from the Department and the Premier’s office since Thursday have been fruitless. The Premier’s office referred us to the department, but emails to three people including Ncalane on Thursday, Friday and Monday, were left unanswered and though a promise to respond was made on the phone on Monday, by the time of publication nothing had been received
Ndwedwe community leader Zibonele Ngcobo said the two drownings could have been avoided. He said the community had been excited about the construction of a new bridge. “But it stopped and we don’t know what happened.”
Blessed Gwala (IFP), member of the Transport, Community Safety and Liaison Portfolio Committee in the KwaZulu-Natal Legislature, said Nkonyeni should take responsibility “for the numerous incomplete projects across the province”. He called on Nkonyeni to “institute an urgent investigation into the whereabouts of the funds earmarked for the construction of the Ndwedwe bridge project” and to complete the bridge without further delay.